| WEEK OF AUGUST 24 – AUGUST 28 |
WEEK OF AUGUST 31 -SEPTEMBER 4 |
|
|
Sterling Avenue Greenfield Street |
No work is scheduled. |
The Contractor is scheduled to fine grade and pave the roadway with hot mix asphalt. |
| Elm Street (Division – Cecil) |
The Contractor is scheduled to continue grading the roadway and installing the new gravel road base. | The Contractor is scheduled to begin concrete curb and gutter construction. The Contractor will notify residents when they will not have access to their driveway. |
| Reed Street (Washington to Cecil) | The Contractor is scheduled to begin concrete curt and gutter construction. The Contractor will notify residents when they will not have access to their driveway. | The Contractor is scheduled to begin driveway apron and sidewalk construction. |
| Henry Street (Douglas to Monroe) | No work is scheduled. | No work is scheduled. |
Notes: 1) This schedule could vary depending on site conditions and weather.
2) Please contact the Department of Public Works at 920-886-6240 if you have any questions or concerns during the construction project, especially related to safety.
3) Our inspector and/or the contractor will be contacting customers prior to connecting the new water services, which will require a water service interruption. We will work to make the connection during a time that is convenient for the customers and the contractor.
4) Please return the Property Owner Authorization Form to the Department of Public Works as soon as possible.
| WEEK OF JULY 13 – JULY 17 |
WEEK OF |
|
|
Sterling Avenue Greenfield Street |
The Contractor is scheduled to continue sewer and water lateral construction from the street to the homes. |
|
| Elm Street (Division – Cecil) |
The contractor is scheduled to continue sewer and water service construction and begin storm sewer construction. |
|
| Reed Street (Washington to Cecil) | The Contractor is scheduled to finish water main construction. | |
| Henry Street (Douglas to Monroe) | No work scheduled – rest period |
Notes: 1) This schedule could vary depending on site conditions and weather.
2) Please contact the Department of Public Works at 920-886-6240 if you have any questions or concerns during the construction project, especially related to safety.
3) Our inspector and/or the contractor will be contacting customers prior to connecting the new water services, which will require a water service interruption. We will work to make the connection during a time that is convenient for the customers and the contractor.
4) Please return the Property Owner Authorization Form to the Department of Public Works as soon as possibl8
| WEEK OF JULY 13 – JULY 17 |
WEEK OF |
|
|
Sterling Avenue Greenfield Street |
The Contractor is scheduled to continue sewer and water lateral construction from the street to the homes. |
|
| Elm Street (Division – Cecil) |
The contractor is scheduled to continue sewer and water service construction and begin storm sewer construction. |
|
| Reed Street (Washington to Cecil) | The Contractor is scheduled to finish water main construction. | |
| Henry Street (Douglas to Monroe) | No work scheduled – rest period |
Notes: 1) This schedule could vary depending on site conditions and weather.
2) Please contact the Department of Public Works at 920-886-6240 if you have any questions or concerns during the construction project, especially related to safety.
3) Our inspector and/or the contractor will be contacting customers prior to connecting the new water services, which will require a water service interruption. We will work to make the connection during a time that is convenient for the customers and the contractor.
4) Please return the Property Owner Authorization Form to the Department of Public Works as soon as possibl8